58. | Alia can complete an assignment in 5 days and Babar can complete the same assignment in 20 days. The time taken by both Alia and Babar to complete the assignment working together is? | |
A. | 3 days | |
B. | 5 days | |
C. | 4 days | |
D. | 2 days | |