14. | A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work ? | |
A. | 75/8 days | |
B. | 44/6 days | |
C. | 48/5 days | |
D. | None of Above | |