26. | Efficiency of Rashid and Danish are in the ratio 5:8. If Danish takes 51 days less than Rashid to complete the work, find the time taken by Rashid to complete the work. | |
A. | 85 days | |
B. | 126 days | |
C. | 118 days | |
D. | 136 days | |