Basic Maths Data Intensity 2 :: Discussion


1.If 3 men or 4 women can construct a wall in 43 days, then the number of days that 7 men and 5 women take to construct it is ?
A.12 days
B.14 days
C.16 days
D.18 days
Answer:  Option  A
Explanation:

3 men does same work as 4 women in 43 days.

multiply 3 and 4 and 43 for a supposed amount of total work (516).

Now calculate how much work is done by 3 men in one day by dividing 516 by 43 (12). Then calculate one man work in one day by dividing 12 by 3 (4).

Same (12) amount of work is done by 4 women in one day. so one women does 12/4 (3) in one day.

now see there are 7 men and 5 women in the final team.
total amount of work in one day will be

7(4)+5(3) = 43

Now divide total work (516) by total work in one day (43) to get the answer (12)

Tutorial Link:
Published by:Michael Daani

Comments are not available

Post your comments here:

Optional

Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers