13. | A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave? | |
A. | 8 | |
B. | 7 | |
C. | 6 | |
D. | 5 | |