10.Kamal will complete work in 20 days. If Suresh is 25% more efficient than Kamal, he can complete the work in days ?
A.12
B.14
C.16
D.18
Answer:  Option  C
Explanation:

Work done by Kamal in 1 day = 1/20
Work done by Suresh in 1 day = (1/20) × (125/100) = 5/80 = 1/16
=> Suresh can complete the work in 16 days