10. | Kamal will complete work in 20 days. If Suresh is 25% more efficient than Kamal, he can complete the work in days ? | |
A. | 12 | |
B. | 14 | |
C. | 16 | |
D. | 18 | |
Answer: Option C | |
Explanation: | |
Work done by Kamal in 1 day = 1/20 |
|