11. | A can do a certain job in 12 days. B is 60% more efficient than A. The number of days it takes for B to do the same piece of work, is ? | |
A. | 12/6 days | |
B. | 15/2 days | |
C. | 23 days | |
D. | 34 days | |
Answer: Option B | |
Explanation: | |
Ratio of time, taken by A and B = 160 : 100 = 8 : 5 |
|