Time and Work - Data Intensity 2 :: Discussion


7.A can lay a railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in_____?
A.4
B.9.6
C.9
D.10
Answer:  Option  B
Explanation:

Tutorial Link:
Published by:Michael Daani

Comments are not available

Post your comments here:

Optional

Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers