Time and Work - Data Intensity 2 :: Discussion


14.A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?
A.5
B.6
C.7
D.8
Answer:  Option  C
Explanation:

Tutorial Link:
Published by:Michael Daani

Comments are not available

Post your comments here:

Optional

Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers