GAT Subject
Engineering
Computer Science Civil Engineering Chemical Engineering Agricultural Engineering Mechanical Engineering Electronics and Communication
| 2. | If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days? | |
| A. | 4 | |
| B. | 8 | |
| C. | 12 | |
| D. | 16 | |
| Answer: Option D | |
| Explanation: | |
|
12 men work 8 hours for 10 days x men work 12 hours for 5 days x = (12*8*10)/(12*5) = 16 men |
|
| Tutorial Link: |