8.Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm. At what time is the task completed?
A.12:00 pm
B.2:00 am
C.12:00 am
D.10:00 pm
Answer:  Option  C
Explanation:

Jameel works for 5 hours. So he completes 5/15 = 1/3 of the task Nasir has to complete 2/3rd of the task 12*2/3 = 8 hours are needed. He completes the task at 12:00 am.