15.A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X?
A.9
B.10
C.11
D.12
Answer:  Option  D
Explanation:

Part of work completed by A in a day = 1/X Part of work completed by B in a day
= 1/(X+5) (1/X)+(1/(X+5))

= 1/6 (2X+5)/(X²+5X)

= 1/6 X²+5X

= 6(2X+5) X²-7X-30

=0 Solving, X=10