19.C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
A.10 days
B.12 days
C.8 days
D.9 days
Answer:  Option  A