GAT Subject
Engineering
Computer Science Civil Engineering Chemical Engineering Agricultural Engineering Mechanical Engineering Electronics and Communication
22. | P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the johow many days does P alone need to finish the remaining work? | |
A. | 8 | |
B. | 6 | |
C. | 4 | |
D. | 2 | |