Time and Work - Data Intensity 2 :: Discussion


28.A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in__days.
A.5 5?11
B.4 5?11
C.6 4?11
D.6 5?11
Answer:  Option  A
Explanation:

Tutorial Link: