13.If 28 men can finish a work in 15 days, 21 men can finish the same work in?
A.12 days
B.14 days
C.18 days
D.20 days
Answer:  Option  D
Explanation:

Time and Men are inversely proportional. Time taken by 28 men to finish the work = 15 days Time taken by a man to finish the work
= 15*28 days Time taken by 21 men = (15*28)/21 = 20 days