4. | P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left? | |
A. | 8/15 | |
B. | 7/15 | |
C. | 11/15 | |
D. | 2/11 | |