37. | A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ? | |
A. | 10 days | |
B. | 11 days | |
C. | 15 days | |
D. | 20 days | |