7. | A can lay a railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in_____? | |
A. | 4 | |
B. | 9.6 | |
C. | 9 | |
D. | 10 | |