Basic Maths Data Intensity 2 :: Discussion


8.P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?
A.10 days
B.13 days
C.15 days
D.17 days
Answer:  Option  C
Explanation:

Tutorial Link:
Published by:Michael Daani

Comments are not available

Post your comments here:

Optional

Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers