1. A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is?
A. 500 m3 B. 1000 m 3 C. 1500 m3 D. 2000 m3
View Answer
Discuss forum
Workplace
Report
Published by:Michael Daani
2. If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by_____?
A. Mid-section formula B. Trapezoidal formula C. Prismoidal formula D. All the above
View Answer
Discuss forum
Workplace
Report
Published by:Michael Daani
Published by:Michael Daani
4. The rate of payment is made for 100 cu m (per % cu m) in case of________?
A. Earth work in excavation B. Rock cutting C. Excavation in trenches for foundation D. All the above