Estimating and Costing-Data Intensity 4 Multiple Questions and Answers.




1.Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds____?
A. 2.00%
B. 2.50%
C. 4.00%
D. 5.00%

2.The expected out turn of 2.5 cm cement concrete floor per mansion per day____?
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm

3.While preparing a detailed estimate______?
A. Dimension should be measured correct to 0.01 m
B. Area should be measured correct to 0.01 sqm
C. Volume should be measured correct to 0.01 cum
D. All the above

4.The most reliable estimate is____?
A. Detailed estimate
B. Preliminary estimate
C. Plinth area estimate
D. Cube rate estimate

5.According to ISI method of measurement, the order of the sequence is_____?
A. Length, breadth, height
B. Breadth, length, height
C. Height, length, breadth
D. None of these

»



Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers