Estimating and Costing-Data Intensity 2 Multiple Questions and Answers.
Exercise Questions ::
Estimating and Costing
6. | The measurement is made in square metre in case of_______? |
| |
| A. | Cement concrete in foundation |
| B. | R.C.C. structure |
| C. | Hollow concrete block wall |
| D. | None of these |
|
|
Published by:Michael Daani
7. | Cost of fittings and their fixing is specified for the following sanitary fittings_______? |
| |
| A. | Water closets |
| B. | Flushing pipes |
| C. | Lavatory basins |
| D. | All the above |
|
|
Published by:Michael Daani
8. | For the construction of buildings, the subheads of the estimate are___? |
| |
| A. | Earthwork, Concrete work, Brick work |
| B. | Brickwork, Stone work, Roofing |
| C. | Brickwork Flooring, Wood work, Steel work |
| D. | All the above |
|
|
Published by:Michael Daani
«