Estimating and Costing-Data Intensity 3 Multiple Questions and Answers.




1.The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as___________?
A. Excavation
B. Surface dressing
C. Cutting
D. Surface excavation

2.As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken_____?
A. 1.80 litres for 5 to 10 users
B. 1.20 litres for 15 users
C. 1.35 for 20 users
D. All the above

3.The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_______?
A. 1.5 m 3
B. 2.5 m3
C. 3.5 m3
D. 5.0 m3

4.The area is measured correct to the nearest______?
A. 0.01 sqm
B. 0.02 sqm
C. 0.03 sqm
D. 0.04 sqm

5.In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and?
A. Half breadth of wall on each side
B. Breadth of the wall
C. One fourth breadth of wall on each side
D. None of these

»



Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers