Basic Maths Data Intensity 2 Multiple Questions and Answers.




6.P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
A. 2 days
B. 4 days
C. 6 days
D. 8 days

7.3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
A. 20
B. 30
C. 40
D. 50

8.P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?
A. 10 days
B. 13 days
C. 15 days
D. 17 days

9.A tank can be filled by a pipe in 20 min. and by another pipe in 60 min. Both the pipes are kept open for 10 min. and then the first pipe is shut off. After this, the tank will be completely filled in?
A. 10 min
B. 20 min
C. 30 min
D. 40 min

10.A is thrice as good a work man as B and takes 10 days less to do a piece of work than B takes. B can do the work in?
A. 15 days
B. 14 days
C. 16 days
D. 30 days

«»



Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers