Time and Work - Data Intensity 2 Multiple Questions and Answers.




41.A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___?
A. 8 days
B. 10 days
C. 12 days
D. 15 days

42.A can do a certain work-in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in__?
A. 15 days
B. 20 days
C. 25 days
D. 30 days

43.A and B can do a work in 8 days, 13, and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in___?
A. 4 days
B. 6 days
C. 8 days
D. 12 days

44.P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
A. 6
B. 7
C. 8
D. 9

«



Date to Date Current Affairs 2022

PakMCQs.net

Quick Links

GAT Subject



   Computer Science    English Mcqs    Agriculture    

Engineering



   Computer Science    Civil Engineering    

Technical



   Networking    Electronics    Database    

Past Papers



   Model Papers    FPSC Papers